The project

Place: Wetzikon (ZH)
Customer: Steiner AG (main contractor)
Phases: Implementation and commissioning
Period: 2018-2024
Construction costs: Approx. CHF 250,000,000

 

The Wetzikon hospital will be extended by several buildings between 2018 and 2024 while the existing buildings will be fully renovated. All construction will be performed while hospital operations are ongoing, which creates high demands for management, logistics, safety and executions. The Wetzikon municipality, the building approval authority, therefore required environmental building management (EBM) for the whole duration of the project.

 

Our services

  • Environmental consulting to owner, construction management and companies
  • Sampling and testing of soils, building substance and excavation material with suspected contamination
  • Environmental building preparations (testing of the disposal/drainage concept, machine list, etc.)
  • Planning and implementation of environmental requirements and measures
  • Regular building site inspection to monitor environmentally appropriate project implementation
  • environmental building management (EBM)

Challenges

  • Large construction site with a construction phase of more than six years
  • Very complex project organisation and large number of participating companies and persons
  • Building and restructuring work while the hospital operation continues imposes high demands on organisation and implementation

Project manager:

Daniel Sabathy Divisional manager: Environmental Planning
Diploma in Biological Sciences ETH (Federal Institute of Technology)
dsabathy@ecosens.ch +41 44 839 47 76 More

Lars Schudel Co-divisional manager: Contaminated sites/ Senior project manager: Environmental planning
Certified Geographer
lschudel@ecosens.ch +41 44 839 47 40 More